Brymbo Reclamation

Project Introduction

Since the earliest planning stages in the mid-1990s Scott Wilson has provided geotechnical advice and design services to Brymbo Developments Ltd for the reclamation and re-development of the 92Ha former Brymbo steelworks, near Wrexham in North Wales. The project is partly funded by the Welsh Development Agency  and the fee value is around £800,000.

Project Background

The Brymbo ironworks were originally established in the late 18th century. The works buildings and slag banks were located on one side of a steep valley, and the site area has been widely undermined for coal and ironstone. Following closure in 1990 the remnants left included a road tunnel, deep basements, heavy foundations, and approximately 50m high slopes formed of end tipped and hot poured slags.

In order to reclaim the derelict works for housing and industrial development a massive earthworks operation was required. This saw over 2 million cubic metres of natural and slag materials being excavated and placed in compacted layers within the site boundaries to form new development platforms.

Project Scope

The reclamation has required the design and specification of both the geotechnical and infrastructure related aspects.  The geotechnical input has included earthworks design and specification, treatment of abandoned mine-workings and shafts, slope stability design and remediation, guidance on construction over filled ground and complicated buried topographies.

Issues that have been addressed include: historical slope instability, complex earthworks, potentially expansive steelworks wastes, temporary and permanent slope design, foundation design including consideration of complex settlement problems relating to deep uncompacted fills, and the investigation and treatment of old underground mine workings.

One area of the site presented a significant settlement problem. The underlying 40 metre deep opencast coal site had been restored, some 25 years ago, by end tipping. Settlement analysis and finite element modelling showed that the placement of a stiffer mantle of engineered fill over this older fill would reduce differential settlements to a level that would permit stable housing development.

Value Adding Project Achievements

Close involvement by Scott Wilson’s geotechnical experts from the earliest conceptual design stage and throughout the reclamation has facilitated a major redevelopment despite the very challenging risks and legacies posed by the historical use of the site. This has given the client the confidence to pursue similarly challenging and difficult sites elsewhere in the country.

Related Services

Go

 

View all Services

Find Projects

Sector

Sub Sector

Country

Project Name

Go

 

Contact